
published by |
produced for: |
| Electricity | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| The electricity industry is one of Australia’s largest individual industries, contributing around 1.5 per cent of Australia’s gross domestic product. Australia’s electricity generation sector faces a number of challenges over the medium to longer term, including the need to meet increasing domestic consumption through investment in new assets and policy measures aimed at reducing greenhouse gas emissions. Over the past decade, final consumption of electricity in Australia increased at an average annual rate of 3.3 per cent. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Industry structure | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| The National Electricity Market (NEM) was established in 1998, to allow for market determined power flows across the Australian Capital Territory, New South Wales, Queensland, South Australia and Victoria (Tasmania joined in 2005). Western Australia and the Northern Territory are not connected to the NEM primarily because of their geographic distance from the rest of the market. The NEM is comprised of a wholesale sector and a competitive retail sector. All electricity dispatched in the market must be traded through the central spot market. However, electricity retailers and generators also enter into contractual arrangements as a means of managing the risk associated with spot market price volatility. The management of the electricity spot market and the central coordination of the dispatch of electricity from generators is the responsibility of the National Electricity Market Management Company (NEMMCO). This role is scheduled to be transferred to a new body, the Australian Energy Market Operator, on 1 July 2009. The Australian Energy Regulator (AER) monitors the market to ensure participants comply with the National Electricity Law and Rules. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||

|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Production | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Around 230 terawatt-hours of electricity was generated in Australia in 2006-07. Over the past five years, the industry has increased electricity generation by 10 per cent, while the number of customers has increased by around 7 per cent. The majority of Australia’s electricity is produced using coal, accounting for 84 per cent of all fuels consumed by generators (in energy content terms) in 2006-07. This is because coal is a relatively low cost energy source in Australia. It also reflects the abundance of coal reserves along the eastern seaboard, where the majority of electricity is generated and consumed. Black coal is expected to remain the most commonly used fuel in electricity generation. However, given that a large proportion of advanced and less advanced projects will be using natural gas or coal seam methane as fuel, these energy sources will account for an increasing proportion of power generation. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Capacity | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| In 2006-07, Australia’s electricity generation capacity was around 47 000 megawatts. As at the end of October 2008, there were 29 committed electricity generation projects and an additional 92 proposed projects. The combined capacity of the 29 committed projects was 6285 megawatts. The National Electricity Market is linked by six major transmission interconnectors. These interconnectors link the electricity networks in Queensland, New South Wales, Victoria, South Australia and Tasmania. The National Electricity Market electricity transmission and distribution network consists of more than 781 000 kilometres of overhead transmission and distribution lines and more than 102 000 kilometres of underground cables. There are a number of projects which are under development to expand the capabilities of the interconnector system. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||
| capacity interconnector | project details | net impact |
start-up |
||
| Central to northern Queensland |
Stage 2 of a 3 stage project. Constructing a Nebo-Strathmore 275 kV line |
Increase transfer capacity by 80-160MW |
Summer 2008-09 |
||
| Central to northern Queensland |
Stage 3 of a 3 stage project. Constructing a Strathmore-Ross 275 kV line |
Increase transfer capacity by 450-520MW |
Summer 2010-11 |
||
| South-west Queensland to South-east Queensland |
Installation of a 120 MVAr capacitor bank at the South Pine 275 kV substation |
Increases voltage stability limit by 25MW for Tarong and Gold Coast by 10MW |
Summer 2008-09 |
||
| South-west Queensland to South-east Queensland |
Establishment of the Abermain 275 V substation and installing a 275/110 kV transformer |
Increases voltage stability limit by 25MW for Tarong and Gold Coast by 10MW |
Summer 2008-09 |
||
| South-west Queensland to South-east Queensland |
Installation of a 200 MVAr capacitor bank at Tarong; a fifth 200 MVAr capacitor bank at Greenbank; and a 120 MVAr capacitor bank at the Mt England and South Pine 275 kV substations |
Increases voltage stability limit by 135MW for Tarong and Gold Coast by 50MW |
Summer 2009-10 |
||
| South-west Queensland to northern NSW South-east Queensland to northern NSW |
Installation of a phase angle regulating transformer on the Armidale-Kempsey 132 kV line no.965 |
Removes impact of mid-North Coast 132 kV line rating limitations on Queensland exports to New South Wales |
Summer 2008-09 |
||
| Northern NSW to South-west |
|||||
| South-west Queensland to northern NSW |
Upgrade of the Tamworth-Armidale |
Increases the 15 minute summer day thermal rating of the line |
Summer 2008-09 |
||
| Northern NSW to central NSW Canberra to central NSW Central NSW to Canberra |
Upgrading the supply to Newcastle, Sydney and Wollongong to 500 kV. Involves transformer and 500 kV substation works. |
Reduces thermal limitations, voltage control limitations and reactive power support limitations |
Network support from Summer 2008-09; Augmentation by Summer 2009-10 |
||
| Source: NEMMCO Statement of opportunities, 2008 | |||||
|
|||||
| interconnector | location |
forward capability |
reverse capability |
||
MW |
MW |
||||
| New South Wales to Queensland (QNI) | Armidale to Braemar |
486 |
1 078 |
||
| New South Wales to Queensland (Directlink) | Terrinora to Mullumbimby |
105 |
234 |
||
| Snowy to New South Wales | Murray to Dederang |
3 309 |
1 090 |
||
| Victoria to Snowy | Buronga to Red Cliffs |
1361 |
1 786 |
||
| Victoria to South Australia (Heywood) | Heywood to Tailem Bend |
460 |
300 |
||
| Victoria to South Australia (Murraylink) | Red Cliffs to Berri |
220 |
220 |
||
| Tasmania to Victoria (Basslink expected capability) |
Seaspray to Georgetown |
594 |
469 |
||
| Transmission and distribution | Overhead |
Underground |
|||
| length (km) | 781 383 |
102 725 |
|||
| Sources: Energy Supply Association of Australia, Electricity gas Australia 2008. | |||||
| Prices |
| Australian electricity prices are among the lowest in the world. The average wholesale price of electricity for the NEM as a whole remained relatively constant until 2007. At the beginning of 2007, average market electricity prices increased significantly, largely as a result of record demand combined with tight supply. In particular, drought constrained hydroelectricity generation in the Snowy region, Tasmania and Victoria, and the limited availability of water for cooling in some coal-fired generators led to higher spot market prices. However, electricity prices have since moderated. Occasional price spikes are often caused by factors such as widespread heatwaves, industrial disputes or generator malfunctions. For example, electricity spot prices in South Australia increased considerably in March 2008 following a 15 day heatwave, which encouraged record high electricity demand. However, reduced maximum allowable flows on the Heywood interconnector from December 2007 constrained the available supply. |



